Waco Driveway, Approach and Sidewalk Permits

Waco Elite Concrete sets out the permit rules for driveways, drive approaches and sidewalks in Waco, Texas, where the line falls at the edge of your lot: concrete flatwork on private property, such as a driveway, needs no City permit, while any work in the City's right-of-way, a drive approach or public sidewalk included, needs a right-of-way permit from the Engineering Department.

Most driveway jobs reach the street, so they also touch the apron and approach where a drive meets the street, which has its own City standard. The rules below come from the City of Waco's Inspection Services and Engineering pages, its standard details and its Code of Ordinances, as the City published them in October 2026. City rules change, so confirm current requirements with the City's Engineering Services before any concrete is poured.

Waco Driveway, Approach and Sidewalk Permits, example photo: utility locate flags and paint marks beside a sidewalk
(254) 309-9254

Call or request a free estimate any time, 24/7

What needs a City permit, and what doesn't

Private driveways, patios and walks

The rule comes from Inspection Services' "Do I Need a Permit?" page, and the City's building permit fee schedule matches it: there is no line for flatwork, driveways or patios. A new drive, a replacement drive or a walk that stays on your side of the property line falls under that rule, and our page on driveway installation in Waco covers the job itself.

Retaining walls, carports and covered porches

Some of the work around new concrete does need a permit. Retaining walls 48 inches high or less need none, but a taller wall must be designed by an engineer and go through a Foundation permit. Accessory structures under 200 square feet are exempt; larger ones, and every detached carport, need a Residential Accessory Structure permit, and a deck or covered porch is treated by the City as a Residential Addition, which takes a permit.

Slabs under buildings

A slab that carries a building comes under Waco's residential construction rules: exterior footings at least 12 inches below undisturbed soil, a 6-inch sand base under the slab covered with a 6 mil polyethylene vapor barrier, and an inspection of every pier and foundation before concrete is poured. Before pouring a slab for a metal building or barndominium, check which of these permits the building itself needs; house and shop slabs are on our Waco slab foundations page.

Call or request a free estimate any time, 24/7.

(254) 309-9254

Right-of-way permits for approaches, sidewalks and curbs

The strip between your property line and the face of the street curb, which the City's standard details call the parkway, belongs to a different department. Engineering's FAQ says its permit is needed "Anytime you will be building a drive approach, sidewalk, or curb", and that none of those is included in a building permit. Its right-of-way page requires a Right-of-Way permit for all concrete and utility work in the right-of-way or in utility easements, and it issues concrete permits only to bonded concrete contractors.

Section 22-66 of the Code of Ordinances bars anyone from building, repairing, removing or replacing a sidewalk, curb, gutter, driveway or other concrete work on public property without a permit from the city engineer. When Waco Elite Concrete looks at a driveway job, we'll talk through which parts fall in the right-of-way and which permits that brings.

The City's concrete contractor's bond

The City's Concrete Contractor's Bond form sets that bond at $5,000. The contractor who posts it must maintain the sidewalks, curbs, gutters or other public concrete it builds or repairs for 12 months at no extra cost to the customer. If a repair isn't made within 30 days of written notice, the City Engineer may take bids from three bonded concrete contractors, with the surety paying. The bond covers concrete on public property only.

Permit deadlines and site rules

A sidewalk or driveway permit is cancelled if active work hasn't begun within 60 days of issue, and work started before the permit is in hand pays double the fee. The contractor must barricade and light the work from sundown to sunrise, and all forms and bracing must come off within seven days after the concrete is placed and finished. Inspections are billed at $88.63 an hour, or $132.94 an hour for overtime.

Planning work at the curb? Call or request a free estimate, 24/7.

(254) 309-9254

Right-of-way fees

Engineering's fees were set by City Council Resolution RES-2024-632, passed on August 27, 2024, and took effect on September 1, 2024. They are the City's permit and inspection fees, not the price of the concrete, so ask Engineering for the current table before you apply. What the concrete itself costs is in our Waco concrete price guide.

Batch ticketCity of Waco right-of-way fees
Residential drive approach
$354.51 each
Commercial drive approach
$443.14 each
Pedestrian ramp
$376.67 each
Sidewalk
$0.95 per sq ft
Curb and gutter
$1.92 per linear ft
Concrete flatwork
$70.91 per cubic yd
Structural concrete
$203.85 per cubic yd
ROW permit
$55.53 each
Street cut or opening
$5.32 per sq ft

City of Waco fee schedule, effective September 1, 2024. Confirm current fees with Engineering.

Call or request a free estimate any time, 24/7.

(254) 309-9254

City standards for drive approaches and sidewalks

Residential drive approaches (ST-23B)

Engineering's sheet ST-23B asks for 6 inches of reinforced 3,000 psi concrete at a home's approach, with #4 bars 18 inches on center each way on concrete chairs, run without a break through the drive approach, the drive apron and the sidewalk over 4 inches of base material. The apron is formed at a slope of 1.5% or less, and any slope over 2% is not accepted; for a 4-foot radius the approach slopes 13.0% to 14.8%. Where a new drive meets an existing curb, the curb must be sawed. How that compares with the slab on your side of the line is in the driveway thickness and rebar guide.

Public sidewalks and curb ramps (SW-1)

Sheet SW-1 governs a concrete sidewalk in the right-of-way. Walks and landings are formed at a cross-slope of 1.5% or less, and finished cross-slopes over 2% are rejected; the sheet places construction joints with expansion material at minimum 50-foot intervals, tooled crack-control joints at a spacing equal to the walk's width, and rebar chairs no more than 4 feet apart each way. No change in level greater than ΒΌ inch is permitted. Curb ramps follow the U.S. Access Board's guidelines for the public right-of-way: no steeper than 1:12, at least 5 feet wide, with landings of at least 5 by 5 feet sloped 2% or less. Ramps for shops, offices and apartments are on our ADA ramp page.

Who answers for the public sidewalk

Waco's code makes the abutting property owner "primarily liable in damages" for injuries from a defective sidewalk, curb or gutter, and puts on owners the duty to keep the sidewalk, parkway, curb and driveway abutting their property "in a good and safe condition". In infill areas, the developer, owner or builder has to repair or replace a badly cracked or displaced sidewalk; see sidewalk repair in Waco for the fixes.

Cracked public sidewalk or a sunken approach? Call or request a free estimate, 24/7.

(254) 309-9254

Concrete permits in towns around Waco

Each nearby city writes its own rules, and several ask for more than Waco does. These are their published rules; where a city's pages don't say whether a job needs a permit, ask the city before you pour.

Woodway and Lorena

Woodway's permit list includes "All concrete work such as drives, sidewalks, porches, patios, etc." Its master fee schedule, effective October 1, 2026, charges $100 per drive approach and $35 for a permit to build a street, drive approach, sidewalk, intersection or curb and gutter in the public right-of-way, and working without a required permit doubles the fee. Lorena's permit page lists the same all-concrete-work rule, charges double the permit fees for work done without one, and allows 10 business days for plan review. Our town pages cover concrete work in Woodway and Lorena.

Hewitt, Bellmead and McGregor

Hewitt's master fee schedule lists a Flat Work Permit at $50 minimum plus $0.02 per square foot, and its permit application warns that review can take up to 10 business days. Bellmead charges $75 for residential concrete flatwork, $150 for the first 1,000 square feet of commercial flatwork plus $0.05 for each square foot over that, and $50 for a right-of-way permit for driveway, sidewalk, curb or street construction. McGregor's fee ordinance, effective October 1, 2025, lists flat work at $40 minimum plus $0.02 per square foot. None of the three spells out which jobs the flatwork permit covers, so ask the city about yours. See driveways in Hewitt, Bellmead concrete and McGregor.

Robinson and Lacy-Lakeview

Robinson charges $75 for a stand-alone drive approach permit and inspection, and $100 to $250 for a right-of-way permit depending on digging and street closures; its permit page names pools, decks, fences and retaining walls, asking for engineered plans for walls over four feet, but doesn't say whether a private driveway needs a permit. Lacy-Lakeview requires permits for driveways and sidewalks, retaining walls, foundations and patio covers, among other projects on its list. More on Robinson driveways and concrete in Lacy-Lakeview.

Outside city limits

In unincorporated places such as China Spring and Willow Grove, McLennan County says it "does not have inspection authority or responsibility and can not charge fees" for residential building. New homes must still be built to the International Residential Code used in Waco, with three inspections reported to the county. For a driveway or slab outside city limits, check with the McLennan County Engineer's Office first. Crawford and Bruceville-Eddy contract with Bureau Veritas for permits and inspections, and their published pages don't list which concrete jobs need one, so ask there too.

Call or request a free estimate any time, 24/7.

(254) 309-9254

Permit questions

Do you need a permit to build a driveway in Texas?

It depends on where the driveway is. In Waco, the part on your lot needs no City permit, but the approach in the right-of-way does. In Woodway and Lorena, drives are on the list of concrete work that needs a permit, and a driveway onto a state highway needs TxDOT's permit (below).

What happens if you do a driveway without a permit?

A private driveway in Waco needs no permit to begin with. In the right-of-way, the code requires a permit from the city engineer before any concrete on public property is built or replaced, and work started first pays double the fee. Woodway charges double for a first offense and double plus $200 after that, and Robinson doubles the building permit fee for work without a permit.

Do I need a permit for a sidewalk?

For a public sidewalk in Waco, yes: it takes a right-of-way permit from Engineering, issued only to a bonded concrete contractor, and the fee is $0.95 per square foot. A walk that stays on your own lot counts as private flatwork, and that takes no City permit.

What are the permit fees for the City of Waco?

There are two schedules. Inspection Services' building fees include $0.45 per square foot for residential structures, $200 for Repairs & Alterations and a $15 technology fee per building permit. Engineering's right-of-way fees are in the table above. On both, work started before the permit pays double.

What can a homeowner do without a permit in Texas?

The answer changes from city to city. Inside Waco, the "Do I Need a Permit?" page lists concrete flatwork on private property, fences (front-yard fences up to four feet, rear and side up to six), retaining walls 48 inches or lower and accessory structures under 200 square feet among the work that needs no permit. Woodway asks for a permit on far more: all concrete work, and every accessory building, even a storage building without a permanent foundation.

What is the phone number for the City of Waco, Texas?

For concrete work, two departments matter, and each lists its own number on its City page. Engineering Services issues right-of-way permits for approaches, sidewalks and curbs. Inspection Services, for building permits, is in the Dr. Mae Jackson Development Center, 401 Franklin Ave., open Monday to Friday, 8 a.m. to 5 p.m.

How to apply for TxDOT driveway permit?

The property owner or an authorized representative applies for the access driveway permit, Form 1058, through the local TxDOT district office; for McLennan County that is the Waco District office, at 100 S. Loop Drive. No construction on the highway right-of-way may begin until the applicant has received a fully executed permit and given TxDOT 24 hours' notice. A private residential driveway is capped at 24 feet wide plus the radii.